NO TASK NAME START DATE END DATE DURATION IN DAYS WORKING DAYS DAYS REMAINING STATUS CAUSE FOR DELAY
1 Scrape Lot 12/08/2021 12/12/2021 5 4   Complete
2 Survey Lot 12/23/2021 12/23/2021 1 1   Approved  
3 Sanitary and Gas Undergrounds 12/28/2021 12/31/2021 4 4   Complete  
4 Meter Rack and Underground Electric 01/17/2022 01/20/2022 4 4   Complete  
5 Pour Concrete Driveway 03/26/2022 03/27/2022 2 2   Complete  
6 All Utility Connections 03/29/2022 03/31/2022 3 3   Complete  
7 Lot Scrape 03/04/2022 03/05/2022 2 2   Complete  
8 Foundation Preparation for 6 LOTS 03/03/2022 04/23/2022 52 42   Complete  
9 Set Forms 04/06/2022 04/26/2022 21 2      
10 Underground Plumbing and Electiric 04/09/2022 04/11/2022 3 4   Complete  
11 Inspection 04/12/2022 04/12/2022 1 1   Approved  
12 Steal Beam Installation 04/25/2022 04/29/2022 5 5      
13 Frame 6 LOTS 04/25/2022 05/31/2022 37 5      
14 Trusses (BMC) for 3 houses (first floors) delivered 04/26/2022 04/26/2022 1 1   Complete  
15 Start Framing for 3 lots 04/26/2022            
16 T-Pole's Problem Fixed 04/26/2022 04/26/2022 1 1   Complete  
17 Trusses (BMC) for 3 houses (second and third floors) delivered 04/28/2022 04/28/2022 1 1   Complete  
18 inspections on 3 lots 8, 9, 10 for underground plumbing 04/29/2022 04/29/2022 1 1   Passed  
19 Framing Roof 05/02/2022 05/31/2022 30 18      
20 Inspection for remaining 3 lots              
21 Starting foundation prep for all six houses 05/04/2022            
22 Install Sheating 06/01/2022 06/25/2022 25 18      
23 Nail inspection 06/27/2022 06/28/2022 2 1      
24 Install Firewall 06/27/2022 07/02/2022 6 6      
25 Firewall Inspection 07/04/2022 07/05/2022 2 1      
26 Install All Cornice 07/04/2022 07/11/2022 8 7      
27 Install flashing 07/11/2022 07/18/2022 8 7      
28 Install Windows 07/18/2022 07/25/2022 8 7      
29 Rough-in plumbing 07/25/2022 07/27/2022 3 3      
30 Rough-in electrical 07/27/2022 07/30/2022 4 3      
31 Rough-in HVAC 07/30/2022 08/06/2022 8 7      
32 Insulation 08/01/2022 08/06/2022 6 6      
33 Install drywall- Tape and float 08/08/2022 08/19/2022 12 11      
34 Door, Trim, Baseboard and stairs Installation 08/19/2022 08/31/2022 13 11      
35 Paint All Trims, walls, flashings and Railings 08/25/2022 09/09/2022 16 14      
36 Cabinets 09/09/2022 09/14/2022 6 5      
37 Install Countertops 09/14/2022 09/28/2022 15 13      
38 Tile 09/14/2022 09/28/2022 15 13      
39 Install Wood Floors 09/15/2022 09/24/2022 10 9      
40 Install Hardware and Locks 09/12/2022 09/24/2022 13 12      
41 Mirros and Shower Doors 09/12/2022 09/15/2022 4 4      
42 Finish Plumbing 09/12/2022 09/20/2022 9 8      
43 Plumbing Inspection 09/20/2022 09/20/2022 1 1      
44 Finish Electrical 09/20/2022 09/27/2022 8 7      
45 AC TRIM 09/20/2022 09/26/2022 7 6      
46 Carpet and Appliances 09/26/2022 10/01/2022 6 5      
47 Landscaping and Grounds Work 09/19/2022 10/01/2022 13 12      
48 Perform final walk-through inspection 10/03/2022 10/05/2022 3 1      
49 Complete punch list items 10/03/2022 10/15/2022 13 12      
50 Site Final Inspection 10/17/2022 10/18/2022 2 1      
51 Deliver Homes and Development to Owners 10/19/2022 10/20/2022 2 2      