FAIRDALE HOMES CONSTRUCTION TIMELINE |
|
Project Name: |
5702 Fairdale Ln. |
General Contractor: |
Uniform Construction |
Architect: |
|
Start Date & Duration: |
12/20/2021 - 10 Month Build |
NO |
TASK NAME |
START DATE |
END DATE |
DURATION IN DAYS |
WORKING DAYS |
DAYS REMAINING |
STATUS |
CAUSE FOR DELAY |
1 |
Scrape Lot |
12/08/2021 |
12/12/2021 |
5 |
4 |
|
Complete |
|
2 |
Survey Lot |
12/23/2021 |
12/23/2021 |
1 |
1 |
|
Approved |
|
3 |
Sanitary and Gas Undergrounds |
12/28/2021 |
12/31/2021 |
4 |
4 |
|
Complete |
|
4 |
Meter Rack and Underground Electric |
01/17/2022 |
01/20/2022 |
4 |
4 |
|
Complete |
|
5 |
Pour Concrete Driveway |
03/26/2022 |
03/27/2022 |
2 |
2 |
|
Complete |
|
6 |
All Utility
Connections |
03/29/2022 |
03/31/2022 |
3 |
3 |
|
Complete |
|
7 |
Lot Scrape |
03/04/2022 |
03/05/2022 |
2 |
2 |
|
Complete |
|
8 |
Foundation
Preparation for 6 LOTS |
03/03/2022 |
04/23/2022 |
52 |
42 |
|
Complete |
|
9 |
Set Forms |
04/06/2022 |
04/26/2022 |
21 |
2 |
|
|
|
10 |
Underground Plumbing and Electiric |
04/09/2022 |
04/11/2022 |
3 |
4 |
|
Complete |
|
11 |
Inspection |
04/12/2022 |
04/12/2022 |
1 |
1 |
|
Approved |
|
12 |
Steal Beam
Installation |
04/25/2022 |
04/29/2022 |
5 |
5 |
|
|
|
13 |
Frame 6 LOTS |
04/25/2022 |
05/31/2022 |
37 |
5 |
|
|
|
14 |
Trusses (BMC)
for 3 houses (first floors) delivered |
04/26/2022 |
04/26/2022 |
1 |
1 |
|
Complete |
|
15 |
Start Framing
for 3 lots |
04/26/2022 |
|
|
|
|
|
|
16 |
T-Pole's Problem
Fixed |
04/26/2022 |
04/26/2022 |
1 |
1 |
|
Complete |
|
17 |
Trusses (BMC)
for 3 houses (second and third floors) delivered |
04/28/2022 |
04/28/2022 |
1 |
1 |
|
Complete |
|
18 |
inspections on 3
lots 8, 9, 10 for underground plumbing |
04/29/2022 |
04/29/2022 |
1 |
1 |
|
Passed |
|
19 |
Framing Roof |
05/02/2022 |
05/31/2022 |
30 |
18 |
|
|
|
20 |
Inspection for remaining 3 lots |
|
|
|
|
|
|
|
21 |
Starting foundation prep for all six houses |
05/04/2022 |
|
|
|
|
|
|
22 |
Install Sheating |
06/01/2022 |
06/25/2022 |
25 |
18 |
|
|
|
23 |
Nail inspection |
06/27/2022 |
06/28/2022 |
2 |
1 |
|
|
|
24 |
Install Firewall |
06/27/2022 |
07/02/2022 |
6 |
6 |
|
|
|
25 |
Firewall
Inspection |
07/04/2022 |
07/05/2022 |
2 |
1 |
|
|
|
26 |
Install All
Cornice |
07/04/2022 |
07/11/2022 |
8 |
7 |
|
|
|
27 |
Install flashing |
07/11/2022 |
07/18/2022 |
8 |
7 |
|
|
|
28 |
Install
Windows |
07/18/2022 |
07/25/2022 |
8 |
7 |
|
|
|
29 |
Rough-in
plumbing |
07/25/2022 |
07/27/2022 |
3 |
3 |
|
|
|
30 |
Rough-in
electrical |
07/27/2022 |
07/30/2022 |
4 |
3 |
|
|
|
31 |
Rough-in HVAC |
07/30/2022 |
08/06/2022 |
8 |
7 |
|
|
|
32 |
Insulation |
08/01/2022 |
08/06/2022 |
6 |
6 |
|
|
|
33 |
Install drywall- Tape and float |
08/08/2022 |
08/19/2022 |
12 |
11 |
|
|
|
34 |
Door, Trim, Baseboard and stairs Installation |
08/19/2022 |
08/31/2022 |
13 |
11 |
|
|
|
35 |
Paint All Trims, walls, flashings and Railings |
08/25/2022 |
09/09/2022 |
16 |
14 |
|
|
|
36 |
Cabinets |
09/09/2022 |
09/14/2022 |
6 |
5 |
|
|
|
37 |
Install Countertops |
09/14/2022 |
09/28/2022 |
15 |
13 |
|
|
|
38 |
Tile |
09/14/2022 |
09/28/2022 |
15 |
13 |
|
|
|
39 |
Install Wood Floors |
09/15/2022 |
09/24/2022 |
10 |
9 |
|
|
|
40 |
Install Hardware and Locks |
09/12/2022 |
09/24/2022 |
13 |
12 |
|
|
|
41 |
Mirros and Shower Doors |
09/12/2022 |
09/15/2022 |
4 |
4 |
|
|
|
42 |
Finish Plumbing |
09/12/2022 |
09/20/2022 |
9 |
8 |
|
|
|
43 |
Plumbing Inspection |
09/20/2022 |
09/20/2022 |
1 |
1 |
|
|
|
44 |
Finish Electrical |
09/20/2022 |
09/27/2022 |
8 |
7 |
|
|
|
45 |
AC TRIM |
09/20/2022 |
09/26/2022 |
7 |
6 |
|
|
|
46 |
Carpet and Appliances |
09/26/2022 |
10/01/2022 |
6 |
5 |
|
|
|
47 |
Landscaping and Grounds Work |
09/19/2022 |
10/01/2022 |
13 |
12 |
|
|
|
48 |
Perform final walk-through inspection |
10/03/2022 |
10/05/2022 |
3 |
1 |
|
|
|
49 |
Complete punch list items |
10/03/2022 |
10/15/2022 |
13 |
12 |
|
|
|
50 |
Site Final Inspection |
10/17/2022 |
10/18/2022 |
2 |
1 |
|
|
|
51 |
Deliver Homes and Development to Owners |
10/19/2022 |
10/20/2022 |
2 |
2 |
|
|
|
|
|
|
|
|
|
|
|
|